Part 2 - Example
This document provides an overview of order metrics, including calculations for order quantity, MRR, TCB, TCV, and ELP, based on changes made on 8/18/2018.
This example assumes that the customer's bill cycle day is set to the 1st of the month.
On 4/1/2018, you use an Update Product order action to increase the quantity to 13. Zuora then creates the following order metrics:
Order Metric |
Start Date |
End Date |
Value |
Calculation |
---|---|---|---|---|
Order Quantity |
4/1/2018 |
12/31/2018 |
3 |
Change in number of units |
Order Mrr |
4/1/2018 |
12/31/2018 |
15.00 |
Value of Order Quantity × list price (5.00) |
Order Tcb |
4/1/2018 |
12/31/2018 |
135.00 |
Apr-Dec: 9 months × Value of Order Mrr |
Order Tcv |
4/1/2018 |
12/31/2018 |
135.00 |
Apr-Dec: 9 months × Value of Order Mrr |
Order Elp |
4/1/2018 |
12/31/2018 |
216.00 |
Apr-Dec: 9 months × Value of Order Quantity × original list price (8.00) |